Critical Path Calculator
Critical path, float and PERT estimates for any task list.
Calculate the critical path
Separate predecessors with spaces. Write a duration as 4/5/8 (optimistic/likely/pessimistic) for PERT.
Project duration
23.83 days
Critical path
Plan → Design → Build → Test → Launch
Chance of finishing by the deadline
91.6%
expected 23.83 ± 1.57 days
| Activity | Duration | ES | EF | LS | LF | Float | Free float | Timeline |
|---|---|---|---|---|---|---|---|---|
| Plan (critical) | 3 | 0 | 3 | 0 | 3 | 0 | 0 | |
| Design (critical) | 5.33 | 3 | 8.33 | 3 | 8.33 | 0 | 0 | |
| Content | 4 | 3 | 7 | 11.67 | 15.67 | 8.67 | 0 | |
| Build (critical) | 10.33 | 8.33 | 18.67 | 8.33 | 18.67 | 0 | 0 | |
| Copy | 3 | 7 | 10 | 15.67 | 18.67 | 8.67 | 8.67 | |
| Test (critical) | 4.17 | 18.67 | 22.83 | 18.67 | 22.83 | 0 | 0 | |
| Launch (critical) | 1 | 22.83 | 23.83 | 22.83 | 23.83 | 0 | 0 |
Everything stays on this device — your project plan never leaves your browser.
Critical path analysis in four steps
The critical path method finds the longest chain of dependent tasks, which decides the earliest a project can finish. Enter each activity with its duration and what it waits on. The calculator runs the forward pass (earliest start and finish), the backward pass (latest start and finish), and marks every activity with zero total float as critical. The example website launch takes 23.83 days, and only five of its seven activities can delay it.
PERT calculator: odds of finishing on time
Estimates are guesses, so a single duration hides risk. Write a duration as optimistic/likely/pessimistic and this PERT calculator weights them (o + 4m + p) ÷ 6, adds the uncertainty along the critical path, and shows the chance of meeting your deadline. With 26 days available the example has a 91.6% chance, and the same plan against 23.83 days is a coin flip.
Reading float
Float is the slack in the plan. Activities with large float, like Content and Copy in the example, can be resourced flexibly or started late; activities with none need protecting. When two paths tie, both are critical, and the calculator lists them all so you know where a delay would hurt.
Choosing software to manage the schedule
A spreadsheet is fine for a one-off plan; once several people share the schedule you need tooling with dependencies and a timeline. Our comparisons cover project management tools for small teams, construction and marketing agencies.